NYHAMNA 2014 Engineering work for steel/aluminium units executed by Mostostal Pomorze S.A. for Kvearner Stord AS.

Works to be done in 2014/2015:

– 1200 t of steel

–   150 t of aluminium.

Scope of work:

  1. 3D structure modeling.
  2. Workshop documentation.
  3. Lofting documentation.
  4. Material specification.
  5. Weld specification and reporting to the MIPS.
50,7m Fresh Fish Trawler 2014/2015 Full set of class and technical documentation for new building of fishing vessel for Skipasyn ehf.
AASTA HANSTEEN 2014 Engineering for steel units for Aker Egersund AS.
Works to be done in 2014:
– steel structure of subsea construction.
Scope of work:
1. workshop documentation.
2. lofting documentation.
3. material specification.
ASGARD SUBSEA 2014 Engineering for steel units for Aker Egersund AS.
Works to be done in 2014:
– steel structure of subsea construction.
Scope of work:
1. workshop documentation.
2. lofting documentation.
3. material specification.
MOHO NORD
AND
MOHO HASE 1 BIS
2014 Engineering for steel units for Aker Egersund AS.
Works to be done in 2014:
– steel structure of subsea construction.
Scope of work:
1. workshop documentation.
2. lofting documentation.
3. material specification.
EAS 200 2014 Engineering for steel units for AS NYMO.
Works to be done in 2014:
– 1300 pc of pipe support
Scope of work:
1. workshop documentation.
2. lofting documentation.
3. material specification.
FLARE STACK
FOR EDVARD GRIEG
2014 Engineering for steel units for Mostostal Pomorze S.A.
Works to be done in 2014:
– 250 t of construction
Scope of work:
1. 3D structure modeling.
2. workshop documentation.
3. lofting documentation.
4. material specification.
5. weld specification and reporting to the MIPS.
m/v FIVEL 2014

Scope of work:

  1. Inclining test with report.
  2. Intact stability booklet.
  3. Damage stability booklet.

Documentation has been prepared for ALKOR Sp. z o.o.

YCRO NORTH DRAGON 2013/2016 Engineering for steel units for Mostostal Pomorze S.A.
Works to be done in 2013/2016:
– 750 t * 3 of construction.
Scope of work:
1. workshop documentation.
2. lofting documentation.
3. material specification.
YCRO NORTH DRAGON 2014 Engineering for steel units for AS NYMO.
Works to be done in 2014:
– 1300 pc of pipe support,
– outfitting documentation
Scope of work:
1. workshop documentation.
2. lofting documentation.
3. material specification.
ELDFISK II, 2/7S 2013/2014 Engineering for steel units for Mostostal Pomorze S.A.
Works to be done in 2013/2014:
– 750 t of construction (seafastening and grillage)
Scope of work:

  1. workshop documentation.
  2. lofting documentation.
  3. material specification.
  4. weld specification and reporting to the MIPS.
EDVARD GRIEG 2013/2014 Engineering for steel units for Aker Egersund AS.
Works to be done in 2013/2014:
– 2700 t of construction
Scope of work:

  1. workshop documentation.
  2. lofting documentation.
  3. material specification.
  4. weld specification and reporting to the MIPS.
NB428 2013/2014 Workshop and lofting documentation for hull structure and outfitting of naval ship.Structure has been executed by Crist S.A. for Karstensen Shipyard A/S.
EDVARD GRIEG 2013/2014 Engineering for steel units executed by Mostostal Pomorze S.A. for Kvearner Stord AS.
Works to be done in 2013/2014:
– 3000 t of construction
Scope of work:

  1. 3D structure modeling.
  2. workshop documentation.
  3. lofting documentation.
  4. material specification.
  5. weld specification and reporting to the MIPS.
TYRA 2013 Engineering for steel units executed by Mostostal Pomorze S.A. for Bladt Industrie AS
Works to be done in 2013:
– 300 t of constructions
Scope of work:
1. lofting documentation preparation.
2. material specification preparation and reporting to system.
3. weld specification preparation and reporting to system.
m/v HELGA MARIA 2013 Technical and workshop documentation of modification m/v Helga Maria.Conversion has been executed in Poland by Alkor Sp. z o. o.
m/v WILLEM DE VLAMING 2013 Execution of inclining experiment with report for Energomontaż-Północ Sp. z o.o.
NB921 2013/2014 Modification of hull structure and outfitting documentation of new building tanker.Structure has been executed by Odys Group.
TORBAS 2012/2014 Workshop and lofting documentation of hull structure, outfitting and piping system for new building fishing vessel.Structure has been executed by Ship Repair Yard Nauta S.A. for Stadyard AS.
Troll A TPC34 2012/2013 Engineering for steel units executed by Mostostal Pomorze S.A. for Aibel AS.
Works done in 2012:
– approx. 150 of various fabrication units
– approx. 740 sheets of steel drawings
– approx. 1 160 t of constructions
Scope of work:

  1. workshop documentation preparation.
  2. lofting documentation preparation.
  3. material specification preparation and reporting to system.
  4. weld specification preparation and reporting to system.
HEROS 2012 Class and technical documentation for tug conversion for change class to ” FIRE FIGHTING SHIP I”
CENTAUR II 2012 Class and technical documentation for tug conversion for change class to ” FIRE FIGHTING SHIP I”
KOMMANDOR CALUMN 2012 Design, workshop documentation preparation and technical supervising of ship       rebuilding.
SVALIN 2012 Engineering for 71 steel construction drawings for project SVALIN executed by PUP GOTECH Sp. z o.o. for Aker Egersund AS.
Scope of work:

  1. workshop documentation preparation.
  2. lofting documentation preparation.
  3. material specification preparation and reporting to MIPS.
  4. weld specification preparation and reporting to MIPS.
OSX Drilling Package
Unit 01311 and 01911
2012 Engineering for 7 steel modules for project 01311 and 5 steel modules for project 01911 executed by Mostostal Pomorze S.A. for AS Nymo:
– approx. 150 of various fabrication units
– approx. 740 sheets of steel drawings
– approx. 1550 pipe support drawings
– approx. 1 160 t of constructions.Scope of work:

  1. workshop documentation preparation.
  2. lofting documentation preparation.
  3. material specification preparation.
  4. weld specification preparation.
ELDFISK 2/7 S 2012 Engineering of the topside module steel units executed by Mostostal Pomorze S.A.,  Energomontaż-Północ Gdynia Sp. z o.o. and Morska Stocznia Remontowa S.A.  for Aker Egersund AS for the Ekofisk 2/4 Z platform:
– over 700 of various fabrication units
– approx. 900 sheets of drawings
– approx 1 820 t of steel construction
Scope of work:

  1. workshop documentation update with pos. numbers and weld numbers.
  2. lofting documentation preparation.
  3. material specyfikation update in MIPS.
  4. weld specification preparation and reporting to MIPS.
EKOFISK 2/4 Z 2012 Engineering of the topside module steel units executed by Mostostal Pomorze S.A., Energomontaż-Północ Gdynia Sp. z o.o. and Morska Stocznia Remontowa S.A.  for Aker Egersund AS for the Ekofisk 2/4 Z platform:
– over 700 of various fabrication units
– approx. 900 sheets of drawings
– approx 1 820 t of steel construction
Scope of work:

  1. workshop documentation update with pos. numbers and weld numbers.
  2. lofting documentation preparation.
  3. material specyfikation update in MIPS.
  4. weld specification preparation and reporting to MIPS.
SIA 2011 Class and workshop documentation for superstructure of a new deck for CT Offshore A/S.
m/v LEINEBJORN 2011 Class and lofting documentation for ship with outfitting and pipe system for Karstensen Shipyard A/S.
42m FREEZER 2011 Class and technical dozumentation for hull and naval pipe systems for Skipasyn ehf.
m/v HAVSNURP 2011 Workshop and lofting documentation for outfitting and hull construction for Karstensen Shipyard A/S.
CATAMARAN
14,95 x 10m
2011 Class, workshop and lofting documentation for steel hulls with deck, superstructure and wheelhouse, outfitting and naval pipe system.
Double ended ferry
FUR FERRY
2010 Technical, workshop and lofting documentation for Crist S.A.
Documentation of:

  1. hull, deck and wheelhouse.
  2. part of deck outfitting.
  3. naval pipe system.
BUCKET WHEEL
EXCAVATOR
PE100 – 300
PE100 – 800
2010 Documentation for steel construction for two types of bucket wheel excavators for Mostostal Pomorze S.A.
 WORK BOAT 12,5m 2010 Technical and workshop documentation for deck outfitting, hull construction and pipe systems for Stord Maskin Invest A/S.
Newfoundland
ARROW & ALERT
2010 Preparing reconstruction concept for two twin-ships NF “”ARROW”” and NF “”ALERT”” for Vidir.
The concept concerned:
1. alteration of fishing system “Long linnig”.
2. alteration of fishing system “Long linning” and ship extention by 8m.
m/v LEINEBJORN 2010 Workshop and lofting documentation for outfitting and hull construction for Karstensen Shipyard A/S.
m/v PAULA 2010 Workshop and lofting documentation for outfitting and hull construction for Karstensen Shipyard A/S.
HSSB NB-124
Double-end ferry
2010 Bov Visor and Bov Ramp – technical documentation with 3D model.
Double ended
day ferry
2010 Shore ramp – cooperation with preparing concept documentation and technical documentaton with 3D model.
Cattle Carrier
Conversion
2010 Side door for filling Feed Silos – technical documentation with 3D model and workshop documentation.
m/v  GOLLENES 2010 Workshop and lofting documentation for outfitting and hull construction.
 BERGEN TROLL 2010 Class documentation for inner side.
m/v ATLANTSVARID 2010 Scope of documentation: Class drawings of General Arrangement.
NORTHREN BRIDGE
IN WARSAW
2009 Workshop and lofting documentation od WD 15.1;WD 15.2; WD 15.3 of Northern Bridge in Warsaw for Mostostal Pomorze S.A.
NB 6687/1
and
NB 165/1
2009 Various workshop and lofting documentation for Stocznia Gdańsk S.A.
FLOODGATE RAMP 2009 Workshop and lofting documentation for building of movable ramps in floodgate of Bremen Hafen harbour for Crist Ltd.
 NB 409 2009 Workshop (3D) documentation of piping systems for trawler LC 39m. Workshop and lofting documentation for lining and outfitting fish hold for Odys Shipyard Ltd.
JACKUP BARGE THOR 2009 Workshop and lofting documentation of mechanical stoppers for pontoon legs mounted in wind power plant for Mostostal Pomorze S.A.
FISHING BOATS 2009 Realization of contract documentation of 9 types of fising boats (trawlers and seiners) for Deltamarine Ltd.
m/v WIGRY 2009 Updating intact and damage Stability Calculation for chemical tanker for Rem-Service Ltd.
 CATAMARAN 15m 2009 Technical, workshop and lofting documentation of Catamaran LC 15m and  LB 8m for servicing fish-farms.
TANKER TYPU C 2009 Workshop (3D) documentation of piping systems for river tanker for Odys Shipyard Ltd.
ESAB 2008 Workshop documentation of part machinery for Mostostal Pomorze S.A.
m/v VIKLAND
EX
m/v HAVILA FAME
2008 Workshop documentation for Skipapol Ltd.
Supervising of making rebuilding.
Conversion has been executed in Poland by Skipapol Ltd.
m/v KROSSEY 2008 Workshop documentation for Skipapol Ltd.
Supervising of making rebuilding.
Conversion has been executed in Poland by Skipapol Ltd.
LINKSPANS 2008 Technical documentation of two levels linkspans for ferry terminal in Gdynia Harbour
for Hydromega Ltd.
POONTON CRANE
MAJA
2008 Scantling of existing structure for rising working load for PRO.
Semisubmersible production platform GJOA
2007 Engineering of semisubmersible production platform “GJOA”.
52 pcs of assembly sectionover350 various steel section.Scope of documentation:
1. 3D Structure modeling.
2. workshop documentation.
3. lofting documentation.
4. material specification.
5. weld specification and reporting to the MIPS.Structure has been executed by Mostostal Pomorze S.A. for (AKER KVAERNER STORD AS) Aker Solutions Stord AS.
m/v SVANAVAAG 2007 Workshop documentation for Skipapol Ltd.
Supervising of making rebuilding of fishing trawler.
ANTROLLING TANK 2007 Workshop documentation for Skipapol Ltd.
Supervising of making rebuilding.
m/v ATLAS 2007 Workshop documentation for Skipapol Ltd.
Supervising of making the superstructure rebuilding.
Conversion has been executed in Poland by Skipapol Ltd.
NEW BUILDING 265 2007 Workshop, lofting documentation for Skipapol Ltd.
Supervising of new building.
m/s KAPITAN POINC 2007 Technical and workshop documentation of making rebuilding for hatch covers under PRS approval for Etmal Ltd.
H-6E
Semi Driling Rig-BETA
2007 Engineering of semi drilling rig H6e Alfa.Scope of documentation:

  1. workshop documentation
  2. lofting documentation
  3. material specification
  4. weld specification and reporting to the MIPS.

Structure has been executed by Mostostal Pomorze S.A. for AKER SOLUTIONS STORD AS.

LINKSPAN FOR
PONTOON
2007 Class, technical and workshop documentation of linkspan for floanting quey in Gdańsk Harbour for Euro-Cynk Ltd.
m/v WIGRY 2006 Intact and Damage Stability Calculation for chemical tanker for Rem-Service Ltd.
m/v STAS 2006 Class and workshop documentation for Skipapol Ltd.
Supervising of making rebuilding.
Conversion has been executed in Poland by Skipapol Ltd.
H-6E
Semi Driling Rig-ALFA
2006 Engineering of semi drilling rig H6e Alfa.Scope of documentation:

  1. workshop documentation
  2. lofting documentation
  3. material specification
  4. weld specification and reporting to the MIPS.Structure has been executed by Mostostal Pomorze S.A. for AKER SOLUTIONS STORD AS.
HATCH COVERS 2006 Class and technical documentation of the hatch covers for Mac Gregor.
SAN DIEGO TANKER 2006 Coping technical documentation to electronic version  E001 of Tanker 200 000 DWT for Aker Brevik AS.
m/v BORKUR 2006 Workshop documentation for Skipapol Ltd.
Supervising of making the superstructure rebuilding. Documentation for RSW system.
Conversion has been executed in Poland by Skipapol Ltd.
m/v SYKLUS 2006 Workshop documentation for Skipapol Ltd.
Supervising of making rebuilding.
Conversion has been executed in Poland by Skipapol Ltd.
m/v FALCON 2006 Second design stage of class and technical documentation for Diamar Spa.
m/v BJARNI OLAFSSON 2006 Technical and workshop documentation for Skipapol Ltd. Supervising of making rebuilding.
Conversion has been executed in Poland by Skipapol Ltd.
m/v BRYNJOLFUR 2006 Technical and workshop documentation for Skipapol Ltd. Supervising of making rebuilding.
Conversion has benn executed in Poland by Skipapol Ltd.
m/v DAR MŁODZIEŻY 2006 Technical and workshop documentation for Enamor Ltd
equipment wheelhouse and student’s cabin
modernization of ventilation
construction of platform to wheelhouse
Supervising of making aluminium wheelhouse for Gdynia Maritime University.
28,9 m
TRAWLER/LONGLINER
2005 Technical documentation  of new 28,9 m Trawler/Longliner for SkipaSyn ehf.
RO-RO LINSPAN 2005 Technical, workshop, supervising and mounting linkspan for ro-ro ships in Gdynia Harbour for Hydromega Ltd.
ORMEN LOUNGE 2005 Workshop documentation of onshore constructions
Navalconsulting Szczecin.
m/v BERGUR VE-44 2005 Technical and workshop documentation for Skipapol Ltd. Supervising of making rebuilding.
Conversion has been executed in Poland by Skipapol Ltd.
m/v WAKER 2004 Workshop documentation of repair for URS and Skipapol Ltd. Supervising of making repair.
m/v OCEAN CONCORD 2004 Class and technical documentation of rebuilding for Skipapol Ltd.
Supervising of making rebuilding.
Conversion has been executed in Poland by Skipapol Ltd.
m/v ATLANTIC
PROTECTOR
m/v ATALNTIC
PRESERVER
2004 Class, technical and workshop documentation of conversion for SkipaSyn ehf. and Skipapol Ltd. Supervising of making conversion.
Conversion has been executed in Poland by Skipapol Ltd.
m/v KARINA 2004 Technical documentation of conversion for SkipaSyn ehf.
m/t KRONOS 2004 Class and technical documentation of making repair for SkipaSyn ehf.
m/t MOCARZ 2004 Class and technical documentation of making repair for WUŻ Gdynia.
m/v FALCON 2004 Class and technical documentation of new ship for Diamar Spa – Italy.
m/v ANTARCTICA 2004 Class and technical documentation of making repair for Diamar Spa – Italy.
ALUMINIUM
SUPERSTUCTURE
2004 Workshop documentation of new aluminium superstructure for Aluship Technology Ltd.
Aluminium superstructure has been built in Poland Aluship  Technology Ltd.
UPPER LINKSPAN 2004 Technical, workshop documentation andsupervising of linkspan for upper deck  ferries for Hydromega Ltd.
m/v BJORG JONSDOTTIR
EX
m/v BIRKILAND
2004 Class, technical and workshop documentation for Skipapol Ltd.
Supervision of making repairs.
Conversion has been executed in Poland by Skipapol Ltd.
m/v NEWFOUNDLAND LYNX 2004 Class, technical and workshop documentation for Skipapol Ltd. and FPI. Supervision of making repairs.Delivery ship equipment.
Conversion has been executed in Poland by Naval  Shipyard Gdynia S.A.
m/v KAP 2003 Class, technical and workshop documentation for Skipapol Ltd.
Supervision of making repairs.
Conversion has been executed in Poland by Skipapol Ltd.
m/v ALPHONSE LETZER 2003 Class, technical and workshop documentation for URS.
Supervision of making repairs.
MOTOR YACHT 2003 Class and technical documentation of new boat for North Sea Ship.
m/v FLORIDA 2003 Supervision of making repairs by Skipapol Ltd.
m/v SANDVIC 2003 Technical and workshop documentation for Skipapol Ltd. Supervision of making repairs.
SRV – 1 2003 Class, technical and workshop documentation for Diamar Spa – Italy.
Building of new fully equipped boat.
TRAWLER 36,5 m 2003 Technical  and workshop documentation for new building for Crist Ltd.
Base on this project has been built vessel in Poland by Crist Ltd.
CLAM VESSEL 2003 Partly class and technical documentation for new project  for SkipaSyn ehf.
m/v BJARNI
SAEMUNDSSON
2003 Class, technical and workshop documentation of conversion for SkipaSyn ehf.
m/v ARNAR 2003 Class, technical and workshop documentation of conversion for SkipaSyn ehf.
GANGWAY 2003 Technical and workshop documentation of adjustable and of gangway which had been mounted on Helskie pier in Harbour of Gdynia for Hydromega Ltd.
m/v GOLLENES 2003 Modification of pipe and electrical system, outfitting work in new insert part for Crist Ltd.
ALUMINIUM
SUPERSTRUCTURE FOR
MEGA YACHT
2002 Workshop documentation of new aluminium superstructure for Aluship Technology Ltd.
Aluminium superstructure for mega yacht has been built in Poland by Aluship  Technology Ltd.
LINKSPAN 2002 Class, technical and workshop documentation of linkspan with execution of the mounting on Helskie II pier in Harbour of Gdynia for Hydromega Ltd.
m/v DEURLOO 2002 Technical documentation for URS and supervising of repair.
Conversion of m/v Deurloo with cooperation with Velasalan Nauta Shipyard Ltd.
m/v KONTROLER 8 2002 Class docking repair and modification of fishing boat for UM Gdynia.
TRAWLER 21,95 m 2002 New building project of the fishing vessel 21,95 m, class and technical documentation under DNV rules for Crist Ltd.
Base on this project has been built vessel in Poland by Crist Ltd.
PONTON 2002 Technical analyze of conversion in several options for WUŻ PUŻiP.
m/v MAŁŻ II 2001 Technical analyze of conversion in several options for PRCiP Ltd.
m/v FRAMNES 2001 Class and technical documentation of decks and of fish hold conversion for Hradfrystihusid ehf.
Partly conversion of m/v Framnes with cooperation with Velasalan Nauta Shipyard Ltd.
GANGWAY LADDER 2001 Technical and workshop documentation of the gangway ladder for Nauta Stal Ltd.
Base on this documentation Nauta Stal Ltd. has made two (2) set of gangway ladder for Greece.
m/s GERDA MARIA 2001 Class dwg of General Arrangement for S.R. Nauta S.A.
Conversion has been executed in Poland by Nauta Shiprepair yard S.A.
SAR 2001 Workshop documentation of new aluminium boat 46m for Aluship Technology Ltd.
Conversion has been executed in Poland by Aluship Technology Ltd. for Fassmer Shipyard- German.
m/v UNION BEAVER 2001 Class and technical documentation for URS. Conversion of m/v Union Beaver has been executed in Poland by Velasalan Nauta Shipyard Ltd.
FORECASTLE DECK 2001 Class and technical documentation of new forepart for Calpol Ltd. CONSTRUCTION. Base on this documentation vessel has been converted in GSR.
HATCH COVERS 2001 Class and technical documentation of the hatch covers for Mac Gregor. Base on this documentation hatch covers has been built in GSR.
m/s ARCTIC PRAWNS 2001 Scope of documentation for SkipaSyn ehf. and Clearwater Ltd.
Class and technical documentation of conversion.
Technical documentation of boom suspension.
Conversion of m/s Arctic Prawns has been executed in Poland by Velasalan Nauta Shipyard Ltd.
m/v HOFFEL 2000 Scope of documentation for VNS Ltd.
Technical documentation of new lengthening part.
Technical documentation of boom suspension.
Safety Plan.
Conversion of m/v Hoffel has been executed in Poland by Velasalan Nauta Shipyard Ltd.
CANADIAN SHIP 2000 Scope of documentation for SkipaSyn ehf.
GA – Plan.
Safety Plan.
Class documentation of new wheelhouse.
Class documentation of navigation lights arrangement.
m/v BJARNI 2000 Scope of documentation for SkipaSyn ehf.
Class documentation of navigation lights arrangement.
Class documentation of boom suspension.
m/v ANDVARI 2000 Free board calculation for SkipaSyn ehf.
m/v ANDEY 2000 Scope of documentation SkipaSyn ehf.
Class documentation of propeller nozzle.
Class documentation of rudder blade and pintle bearing.
m/v REYKJABORG 2000 Scope of documentation for SkipaSyn ehf.
Class documentation of lengthening part.
Class documentation of new funnel.
m/v GNUPUR 2000 Class and technical documentation of new anti-rolling tank for SkipaSyn ehf.
The tank has been built in Poland by Velasalan Nauta Shipyard Ltd.
m/v SIGHVATUR
BJARNASON
2000 Scope of documentation for SkipaSyn ehf.
Class and workshop documentation of aft part.
Technical dwg of fish hold modification.
Conversion of m/v Sighvatur Bjarnanson has been executed in Poland by Velasalan Nauta Shipyard Ltd.
PAIR TRAWLER 2000 New building project 00-4330, class documentation under DNV rules for SkipaSyn ehf.
TUG BOAT 17m 2000 New building project of the tug boat 17 m, class technical documentation under DNV rules for Crist Ltd.
Base on this project has been built vessel in Poland by Crist Sp. z o. o.
m/v THORLAKUR 2000 New building project of longliner 28,9 m, class technical documentation under IMA rules for Skipasyn ehf. and VNS Ltd.
Base on this project has been built vessel in Poland by Velasalan Nauta Shipyard Ltd.
m/v BERGUR 1999 Scope of documentation for Bergur ehf.
Class and workshop documentation of lengthening part.
Technical and workshop dwg of new accommodation and wheelhouse.
Technical documentation of new forecastle deck.
Conversion of m/v Bergur has been executed in Poland by Velasalan Nauta Shipyard Ltd.
TRAWLER 28,9 m 1999 New building project 99-2890- FV5 & FV7, class documentation under DNV rules  for SkipaSyn ehf.
Base on this documentation has been built two (2) vessels in China in years 2000-2001 for Icelandic Owners.
TRAWLER 21,5 m 1999 New building Project 99-200, class documentation under DNV rules for SkipaSyn ehf.
Base on this documentation has been built nine (9) vessels in China in years  1999-2001 for Icelandic Owners.